9 years 3 months ago #68674
by yankeedawg1
I have had word that the IPF is moving along
Ahead of schedule. Site preparation is going
Take several months. Major chunk of time
All the underground utilities that lay under
The footprint of the building. GA power has stated they will be ready to roll
OK for a cold winter. Dry is the word until
Spring....footings get poured and set
Hanging steel will move. My money says
Ready for spring camp 2017...if we catch a break on weather. Go Dawgs
Go Dawgs!
The following user(s) said Thank You: stevedawg, Buc